load work - queue
loading work into production workstation.
1. Select the asset to load up on the production workstation.
select asset2. Complete pre-use checks if workstation requires it.
Some workstation require the pre-use checks, until they are completed the system will not allow you proceed further.
submit pre-use check3. Then all of the pre-use checks is successful the loading menu will become visible

4. To refresh the list of available work, press on the icon

5. Click on LOAD
Then you selected which item you would like to load first.

6. Click on the item to confirm its correct item to be loaded

7. Click on LOAD

8. Work has been successfully loaded onto the workstation.